Portland Building Overclad Nears Completion

Date: 21 March 2019
Source:
Portland Building Overclad Nears Completion
Photo source
www.bensonglobal.com

Date: 21 March 2019

Progress continues on the overclad of Michael Graves’ post modern icon, The Portland Building.

Benson’s Otay Mesa Assembly Facility completed the last of the 946 curtain wall units this month. Installation on the final two elevations continue with an estimated substantial completion date slated for Mid-April.

Project Manager Melissa Johnson and Field Superintendent Charlie Graham have worked closely with our client Howard S Wright, A Balfour Beatty Organization coordinating the various trades working on this complex site.

The Portland Building’s curtain wall installation close to completion
The Portland Building’s curtain wall installation close to completion
600450 Portland Building Overclad Nears Completion ºÚÁÏ×¨Çø

Others also read

Two landmark NorthGlass projects have taken top honors at the 2026 Glass Magazine Awards, showcasing the possibilities of advanced glass in contemporary architecture.
At GlassBuild America 2026, Booth #1945, Glaston is showcasing its full portfolio of automation solutions spanning tempering, lamination, insulating and mobility glass manufacturing, each built to help processors not just keep pace, but lead.
On August 18, NorthGlass Shanghai Automation Co., Ltd. successfully signed an agreement with Wenxin Group for an automated smart factory project for glass used in whole-house custom furniture.
Solarban® 70 glass brings transparency, solar control and comfort to UT Dallas’ innovative engineering campus.
EnduroShield has been specified for The Ritz-Carlton, Sarasota, helping protect multiple hundreds of shower enclosures across three buildings in a coastal Florida environment.
On Chicago's former Finkl Steel site, high-performance Vitro glass helps turn 1229 W. Concord into a daylight-filled, riverfront-facing model for next-generation life sciences design.

Add new comment