Work is on schedule at the £54million Glass Futures Global Centre of Excellence in St Helens with the steelwork structure now completed.

Contractors Bowmer + Kirkland, who started on site in January, say the next phase of the scheme is already underway with the cladding and external elevations expected to be completed on the 165,000 sq. ft facility by the end of the summer.

B+K’s work on the scheme is expected to complete in January 2023, ready for fit-out by Glass Futures.

The facility has been pre-let to St Helens Borough Council on a 15-year head lease and will be sub-let to Glass Futures which will occupy and manage the building to deliver industry and government backed research and development projects focused on decarbonising glass production. It will also provide a platform for the industry to access an experimental scale furnace to test and run trials for implementation at commercial scale on a state-of-the-art line, both collaboratively and individually.

Delivery of the project was conceived and is being managed by landowner and developer Network Space Developments (NSD), on behalf of a partnership including not-for-profit research organisation Glass Futures, St Helens Borough Council, the Liverpool City Region Combined Authority and UKRI (UK Research & Innovation). NSD will continue to manage the delivery of the project through to practical completion. Earlier this year the building was presold by NSD to global investor Standard Life Investments Property Income Trust, part of abrdn, to secure forward funding and conclude a viable delivery strategy.

"We’re delighted with the progress so far on site with a completion date of January 2023 still very much in our sights. The outline structure of the facility is now visible and symbolises the scale and ambition of both St Helens Council and the Glass Futures project to bring significant investment and skilled jobs back into St Helens and the wider Liverpool City Region economy.

None of this would have been possible without the exceptional partnership formed between NSD, Glass Futures, St Helens Borough Council, the Liverpool City Region Combined Authority and UKRI. The partnership is proud to see the noticeable progress being made on site following the tremendous efforts to achieve this key milestone."

Said Catherine Chilvers, Development Director at Network Space

"We’re making significant progress on site with the steel frame now completed and roofing works commenced. The B+K team is proud to be part of this iconic build for St Helens and its future role in glass manufacturing and development in the area. The scheme is transformational in every sense, not just for the town but also for its future contribution towards zero carbon production in the global glass industry."

Said David Baker, Project Manager on the Glass Futures’ site for B+K

600450 Steelwork completed on £54million Glass Futures’ development ºÚÁÏ×¨Çø

Others also read

The Glass & Glazing Federation (GGF) has announced a new partnership with REHAU, giving businesses within the REHAU Authorised Partner network access to GGF Membership at a preferential rate.
GGF has called for high-performance glazing to play a greater role in UK housing retrofit and fuel poverty policy, highlighting its potential to reduce energy demand, lower household bills and support British manufacturing.
The UK glass and glazing sectors have committed to working in partnership with Government to help turn its ambitions for reindustrialising Britain into investment, skilled jobs, stronger supply chains and sustainable economic growth.
The European Commission’s new Public Procurement Act proposal could reshape how quality, sustainability and EU-origin content are valued in public tenders, with important implications for the flat glass sector.
New solar heat gain restrictions in the National Building Code are transforming Canadian building design, a challenge a panel of industry experts broke down last week at the FGIA Fall Conference.
On 8 September 2026, Glass for Europe took part in a roundtable on energy organised by the European Commission’s DG ENER.

Add new comment

NEWS RELATED PRODUCTS